MCD / DDA / SDMC
Lift NOC & Lift Permission in Delhi

The request for seeking NOC for installation of lift and connecting bridge should be submitted by Proposing Applicants* after obtaining necessary consent from owner(s)/ legal representative(s) of at least 50% of the flats in that staircase (of that block) who shall be beneficiaries upon the installation of lifts in DDA flats. The consent from ground floor flat owners is desirable but not mandatory for seeking NOC by applicants. Application must be complete with all necessary documents/Affidavits and other pre-requisites for issue of NOC and lift installation in DDA flats.
General
Allottees in all the Colonies where services stand transferred to MCD as well as colonies where services are with DDA shall apply to SE(HQ), DDA of concerned Zone. The NOC shall be issued by CE(HQ) after due verification of documents. After the issue of NOC by DDA, the applicants must get modified drawings approved from local Municipal Authority, in the areas which have been de-notified before actual execution of work for successful installation of Lift in DDA flats.
Whom to Apply
While applying for NOC, the following documents/ indemnity bonds/affidavits are required to be submitted:
- Consent for installation of lift in individual block (served by a common stair case) from owner/legal representative of at least 50% of the flats in the stair case of that block. The consent from ground floor owner is desirable but not mandatory.
- Recommendations of the lift manufacturing agency (preferably as per approved list of CPWD) to whom residents are likely to engage for installation of lift with regard to technical feasibility, location of lift well, safety aspects in respect of installation.
- Certificate from registered Structural Engineer/ Architect (on their letter head) stating that the structural design of lift well is as per provisions of National Building Code.
- Four sets of original building plan indicating location of the lift-well duly signed by registered Architect and proposing/secondary applicants.
- Certificate regarding maintenance/operation aspect and safety requirement and bear all the cost for the above operation.
- Undertaking to obtain NOC from Chief Fire Officer, GNCTD (if applicable), Lift Inspector and Power/Electricity Distribution Company.
- NOC from the registered RWA of the particular block in case any shifting of services are involved for lift installation in DDA flats.
- Indemnity Bond from all the Proposing applicants* indemnifying to keep DDA harmless from any claim which anyone may, at any time, crop-up against the DDA.
- The group of proposing members who are beneficiaries of lift shall give an affidavit on stamp paper that there is no unauthorised construction/construction beyond permissible limit including terrace floor of that particular block (the NOC for DDA lift installation shall not be processed till all such unauthorised constructions are removed/regularized). In any case lift shall not be allowed to go up to terrace level at all.
- After examination of the proposal including all technical aspects by Superintending Engineer(Head Quarter) concerned, Director (Housing) & Senior Architect, and on their recommendations, CE(HQ) DDA will issue No Objection Certificate for installation of lift subject to deposition of requisite charges, if any, raised by DDA as discussed in para (xii) below for installation of lifts in DDA flats.
- Where absolutely necessary a provision of connecting bridge/walk way can be considered from the lift well to the landing point.
- A processing fee of Rs.5,000/-(non refundable) per lift will be charged by the DDA after verifying the check list (permission shall be granted within 45 days after submission of all complete acceptable documents). The payment can be made by DD in favor of concerned Sr.AO(CAU),DDA.
Documents Required
* A processing fee of Rs.5,000/-(non refundable) per lift will be charged by the DDA after verifying the check list (permission shall be granted within 45 days after submission of all complete acceptable documents). The payment can be made by DD in favor of concerned Sr.AO(CAU),DDA.
The policy of lift installation in DDA flats, first notified on May 26, 2011, was subsequently modified on August 3, 2012, the urban body said.
It has additionally been referenced in the arrangement that the lift well will be developed adjoining the visually impaired divider so regular light, ventilation and development isn’t influenced and will be an autonomous structure.
To get the NOC for DDA lift installation, the lift should be installed in a manner that the stability of the existing structure is not affected and no weight is transferred on to the current structure.
We are a DDA compliant local body that helps in Installation of Lifts in DDA flats as well as getting NOC for DDA lift installation.
Lifts Rules in Delhi – Elevator Installation
In modern urban living, lifts are no more a luxury, they are a fundamental necessity for independent and safe mobility. This need has led many residents to consider installing elevators in DDA, MCD and CGHS flats. However, they do not have the liberty to alter the structure without legal sanction.. Therefore, it is essential to understand the lift installation rules and regulations in Delhi before commencing any work. This is where our guide steps in to help you understand the correct legal process and start lift installation work in your building without hassles.NOC/Sanction For Lift Installation in DDA/MCD/ CGHS Flats in Delhi
Residents of DDA, MCD, and CGHS flats cannot erect, re-erect or make any alterations to the existing building structure without getting the required NOC/Sanction for the installation of lifts. Any new lift installation work carried out without permission from the DDA or local authority like the MDC or SDMC will result in the construction work being halted and attract legal action under the DDA and DMC Acts of 1957.Why Is It Needed?
Under the lift installation rules in Delhi for any CGHS, MDC and DDA structure, getting an NOC/Sanction is mandatory to confirm-- The lift is safe for the residents to
- The DDA/MCD/ CGHS building will not be damaged during the lift installation work
- The lift installation in the building is carried out in complete compliance with all legal rules and
Permission can be obtained from-
- MCD – if the Maintainance of the Society(Whether MCD Flats or CGHS Flats) falls under its jurisdiction.
- DDA- if the Maintainance of the Society is under jurisdiction of
- Primary– This applicant is the financial contributor for the elevator installation work
- Secondary- A non-financial contributor with no objection to the lift installation .
DDA/MCD/CGHS Flat Lift Installation Rules and Regulations in Delhi and NOC Approval
To get the NOC/Sanction for lift installation in a DDA/MCD/ CGHS building, the rules and regulations listed in the NOC/Sanction Policy must be carefully followed. Let us look at them below-- Consent: Written consent for the installation of the lift must be obtained from at least 50% of the flat owners or residents who use the common staircase, excluding those residing on the ground floor. Consent from ground-floor residents may be taken, but it is not a mandatory
- Independent Structure: For the safety of the main building’s structure, the lift must be separately installed from it. It should be an independent structure and a connecting bridge may be constructed, if needed to support the stability of the main
- Passage Space- There should be at least one meter of space (wherever applicable) in the passage for the residents to safely pass
- Ventilation and Natural Light: The ventilation and natural light of the flats must not be reduced. The lift should be installed against a blind wall or at a safe distance from the existing
- Technical Feasibility Certificate: A certificate of technical feasibility should be provided, by a CPWD-listed and certified lift manufacturer like ShuttleSky
- Compliance with Building and Fire Safety Codes: All provisions of the National Building Code and Fire Safety Codes must be strictly Safety certificates must be submitted by a registered structural engineer and a registered architect.
- Building Plans: Four sets of building plans, duly signed by the registered architect and the proposing flat owners, must be
- Indemnity Bonds and Undertakings: Indemnity bonds and undertakings are mandatory, covering maintenance, safety, electrical and fire compliance, and all legal responsibilities of the resident flat
- Accessibility: The lift design should be friendly and accessible for senior citizens and persons with
- NOC for Shifting Services: If any common services are required to be shifted, an NOC from the Managing Committee of the RWA or CGHS should be
- Terrace Restriction: The lift must not extend up to the terrace level of the
- Filled application form (Appendix A)
- Four sets of building drawings (one on cloth), signed by:
- Consent letter from owners of the block and nearby flats who may be
- Supervision certificate from Architect and Structural Engineer (Appendix B), with copies of their registration
- Proof that you own the flat, such as Sale Deed, GPA, or ownership papers approved by DDA.
- Safety certificate for natural disasters (like earthquake), signed by proposing residents and structural engineer (Appendix C).
- Undertaking by proposing residents that they will pay for lift installation, operation, and maintenance (Appendix D).
- Undertaking from Architect/Structural Engineer confirming that the design follows National Building Code rules (Appendix D2).
- Indemnity Bond on ₹100 stamp paper, saying DDA will not be responsible for any damage or accident (Appendix E).
- Proof of payment of ₹5,000 processing fee by Demand Draft in favour of DDA, New Delhi.
- Technical feasibility certificate from lift company, confirming the lift and bridge can be safely installed.
- Whether they are proposing primary members or secondary
Lifts Rules in Delhi- Elevator Installation
Lifts can be installed in –- Setback area
- Common Area
- Rear or open space They should NOT encroach-
- Public land
- Floor Area Ratio or FAR benefit will NOT be given
Clearance Approvals During Lift Installation Construction Work
❖ Supervision Certification by Architect & Structural Engineer
Confirms that work is being done as per approved plans.❖ Approval for Shifting Common Services, if required
NOC from RWA / CGHS Managing Committee if water lines, cables, etc. are shifted.After Lift Installation For The Completion Certificate
❖ Completion Intimation to DDA / MCD
Architects must inform DDA/MCD authorities that construction is completed as per approval.❖ Lift Inspector Certificate
Clearance from a Government Lift Inspector confirming the lift is safe to operate.❖ Fire Department Clearance (if applicable)
Especially where fire safety systems are affected.❖ Power / Electricity Distribution Company NOC
Clearance for electrical connection and safe power supply to the lift.❖ Final Completion Certificate from DDA / MCD
Only after all above approvals are submitted.Fees Applicable for a DDA Compliant Lift
INR 5000 fee ( Non-refundable) for application processing + development charges INR 25,000 for Colonies A and B, INR 15,000 for colonies E,G, and H, for other colonies including C and D, INR 10,000.Please Note:
- Your application form should be submitted with the correct documents or else it will get rejected.
- Visit the official DDA website to verify current fees and other important details before applying for lift installation in DDA, MCD, or CGHS flats, as fees and provisions may change from time to